March 21, 2014 - Outage Day

  • 12:15pm - outage complete; all compute servers are back on.
  • 11:15am - chilled water is flowing again; we've started to turn back on the compute servers.
  • 10:10am - temperature still stable; chilled water refill expected to start at 11:00am.
  • 7:30am - server room temperature stabilized.
  • 6:45am - chilled water turned off.
  • 6:30am - steamfitters on site.

Scheduled Outage: Friday, March 21, 2014

To make repairs on the chilled water system, the Physical Plant will be shutting down chilled water for several hours Friday morning, starting at about 7:00am.

Chilled water is essential for the correct operation of Biostatistics' main server room in the CSC. When the water stops flowing, the temperature shoots up to 100-110F in about 20-30 minutes.